Note that although this message is date 31st March, it was not received by the PPPS until 30th April when it was forwarded by Lisa Cleverdon of SBC's Legal and Democratic Services department.
From: Debee SkinnerDear Mr Walker
In response to your Freedom of
information request number 488, in which you asked the following
questions
1. A breakdown of all costs
incurred by Southend Borough Council from 1st January 2000 to the
present day in developing plans for road improvements to the Cuckoo Corner
junction and Priory Crescent. This should include the cost of the archaeological
survey, the public inquiry and any other contractors hired to work on the scheme
and its design along with any other relevant expenditure.
I can confirm that a search for
the information has been completed.
Priory Crescent/Cuckoo Corner
(000s)
2001/02
- £287
2002/03
- £428
2003/04
- £1,064
2004/05
- £96
2005/06
- £114
2006/07
- £71
The above figures include
developing plans, archaeological survey, the public inquiry and any other
contractors hired to work on the scheme and its design along with relevant
expenditure.
If you are unhappy with the
service you have received in relation to your request and wish to make a
complaint or request a review of our decision, you should write to Complaints
Officer, Support Services Department,
Kind
regards
Strategic
Planning & Transport, Southend on Sea Borough Council
01702
215408
debeeskinner@southend.gov.uk